Name : Saha Rattana Nakorn Industrial Estate
Establishment : 1994
Director : Mr. Kanapos Khunthong
Phone : +66 3536 4200-1
Fax : +66 2689 7884
103 Moo 4, Bang PhrakruNakhon Luang, Ayutthaya 13260
Industrial Estate Office
103 Moo 4, Bang Phrakru Nakhon Luang, Ayutthaya 13260
Tel. +66 3536 4011-3, +66 3571 6745-6
Fax. +66 3536 4014
- Bangkok: 90 kilometers
- Don Muang Airport: 70 kilometers
- Bangkok Port (Klong Toey): 100 kilometers
- Suvarnabhumi International Airport: 130 kilometers
- Total Area 2,050 rai (820 acres) [1st Phase Development: 1,441 rai (576.4 acres)]
- General Industrial Zone: 867 rai (346.8 acres)
- Residential/Commercial area: 38 rai (15.2 acres)
- Infrastructure and public utilities: 536 rai (214.4 acres)
- General Industrial Zone: 405 rai (162 acres)
Remarks:
*Area available for sale/rent may vary due to zoning changes or land transfers.
*Area available for sale/rent is marketing data.
- General Industrial Zone: 3.5 million Baht/rai
Water Supply System
- Five artesian wells
- Production capacity: 11,960 cubic meters/day
- Distribution capacity: 4,700 cubic meters/day
Electrical Power Supply System
- Provider: Provincial Electricity Authority
- Distribution capacity: 80 MVA
- Power voltage: 22 kV
Road System
- Primary roads: 40 meters wide, four-lane divided traffic
- Secondary roads: 28 meters wide, two-lane divided traffic
- Side streets: 12 meters wide, two-land divided traffic
Telephone System
- Providers: TOT Public Company Limited , TT&T Public Company Limited
- 1,000 direct telephone lines
Wastewater Treatment System
- Capacity: 8,000 cubic meters/day
- Wastewater entering the treatment system: 6,000 cubic meters/day
Incinerator System
- Capacity: 500 kilograms/hour
Fire Protection System
- 36 fire hydrants located every 200 meters along the roads
Ground Condition
- Stiff clay at a depth of 11-14 meters
- Load capacity: 30-50 tons/square meter
Maintenance Fee
- 700 Baht/rai/month
Water Tarif
- 22 Baht/cubic meter (Includes an 8 Baht/cubic meter water conservation fee)
Wastewater Treatment Fee
- 8 Baht/cubic meter with the amount of wastewater calculated based on 80% of piped water used each month
Waste Disposal Fee
- 3 Bath/kilogram