Name: Southern Region Industrial Estate (Songkhla)
Establishment: 1984
Director: Mr.Chaturong Charoensuknor
Phone: +66 7420 6033
Fax: +66 7420 6096
E-mail : Southern.1@ieat.go.th
Website : www.south-ieat.com
Developer : Industrial Estate Authority of Thailand
9/6 Moo 4, Chalung, Hat Yai, Songkhla 90110
Industrial Estate Office
9/6 Moo 4, Chalung, Hat Yai, Songkhla 90110
Tel: +66 7420 6033
Fax: +66 7420 6096
- Hat Yai Airport: 16 kilometers
- Hat Yai District: 15 kilometers
- Songkhla City: 44 kilometers
- Sadao District: 75 kilometers
- Songkhla Deep Sea Port: 47 kilometers
- Malaysia: 82 kilometers
2,247 rai ( 898.8 acres)
Phase 1: 867 rai (346.8 acres)
General Industrial Zone: 205 rai (82 acres)
I-EA-T Free Zone: 114 rai (45.6 acres)
Infrastructure and public utilities: 499 rai (199.6 acres)
Green area: 50 rai (20 acres)
Phase 2: 625 rai (250 acres)
Industrial area: 143 rai (57.2 acres)
Infrastructure and public utilities: 43 rai (17.2 acres)
Green area: 5 rai (2 acres)
Area awaiting development: 422 rai (168.8 acres)
Phase 3: 755 rai (302 acres)
- Phase 1
General Industrial Zone: 24 rai (9.6 acres)
I-EA-T Free Zone: 49 rai (19.6 acres)
-Phase 2/2
General Industrial Zone: 274 rai (109.6 acres)
- Phase 3
General Industrial Zone: 755 rai (302 acres)
Phase 1 General Industrial Zone
I-EA-T Free Zone
Phase 2 General Industrial Zone
Phase 2/2 and Phase 3 General Industrial Zone
Water Supply System
- 2-million-cubic-meter reservoir
- Distribution capacity: 10 cubic meters/rai/day
Electrical Power Supply System
- Two, 50-MVA electric power substations
- Power voltage: 33 kVRoad System
- Primary roads are reinforced concrete, 14 meters wide with four-lane divided traffic.
Telephone System
- 2,048 telephone lines (when fully developed)
Wastewater Treatment System
- Capacity: 3,000 cubic meters/day
- Extended aeration activated sludge (EAAS) system
Maintenance Fee
- General Industrial Zone: 800 Baht/rai/month
- I-EA-T Free Zone: 1,000 Baht/rai/month
Water Tariff
-14 Baht/cubic meter
Electricity Fee
- Charged according to the rate specified by the Provincial Electricity Authority * A 10% reduction in electricity fees is granted for five years.
Wastewater Treatment Fee
- 9.50 Baht/cubic meter (at an average BOD level of 500 milligrams/liter))
- 4.40 Baht/cubic meter (at an average BOD level of 100 milligrams/liter)
[Calculated according to the following formula: Tc = 100 + 7.24Vi + 11.06ViSi/1000 + CP]